The construction process of the project

The construction process of the project

December 1, 2021

The construction process of "New Quality in Didi Digomi" started today. In the first stage of construction, the cave will be prepared for the foundation, which will include a special 1-meter-high cushion with the removal of excess soil from the area. The mentioned area was studied and a geological conclusion was prepared by one of the most powerful companies in Georgia
"Geotexservice", on the basis of whose recommendations the relevant project was prepared.


The project will be fully completed in December 2023 and the apartments will be handed over to the residents in white frame condition where the highest quality materials will be used.

Follow us on our FB page for more information.

The project "New Quality in Didi Digomi" is fully funded

February 1, 2022 An agreement on project financing was signed with Bilderz Ltd and one of...

2022-02-01
Read more

The project "New Quality in Didi Dighomi" will be built with concrete of Heidelberg Georgia

On March 1, an agreement was signed between Bilders Ltd and HeidelbergCement Georgia Ltd.,...

2022-03-01
Read more

The foundation works were completed according to the schedule

March 5, 2022 According to the construction schedule planned today, the foundation slab o...

2022-03-05
Read more

Kubikon performed the constructive part of the project

August 31, 2021 Kubikon has finished construction project of Bilderz Ltd "New Quality in ...